MANCHESTER OLD ROAD
PROJECT OVERVIEW
Coordinating reinstatement in an operational industrial area with controls on noise, dust, and traffic to minimise disruption
Managing potential site hazards like underground services and existing structures, while adhering to CDM 2015 regulations
Delivering a fast-track programme with transparent budgeting and quality assurance
CHALLENGES
- Coordinating reinstatement in an operational industrial area with controls on noise, dust, and traffic to minimise disruption
- Managing potential site hazards like underground services and existing structures, while adhering to CDM 2015 regulations
- Delivering a fast-track programme with transparent budgeting and quality assurance
SOLUTIONS & APPROACH
Bansco adopted a collaborative, value-driven strategy with early engagement to capture any potential additional works required, ensuring proactive problem-solving and close coordination with the client and design team to deliver the original scheme and any changes efficiently within the required timescales under a fixed-price contract.
Key works included:
- Soft strip-outs and deep cleaning
- Recommissioning and certification of M&E systems: electrical, fire detection, HVAC, and drainage
- Repairs to roof (cladding, gutters), elevations (doors, louvres), and external areas (yards, fencing)
- Floor grinding and re-finishing with epoxy
- Phased planning with secure site access and welfare to maintain safety and programme
OUTCOMES & RESULTS
Completed on programme in 12 weeks, the reinstated unit achieved full certification and was ready for market – supporting quick re-letting. Bansco's financial stability and experienced team ensured budget adherence and high-quality outcomes.
A further example of Bansco's industrial reinstatement expertise: efficiently restoring assets to prime condition, minimising downtime, and delivering value in key locations.